Evaluation Implementation Project With Use Earned Value Method ( Object Case : Construction Project of the IAIN Lhoksemawe Laboratory Center Building )

Authors

  • Gofirli Saumah Saumah Universitas Malikussaleh, Faculty Of Engineering, Civil Engineering
  • M Fauzan Department of Civil engineering, Faculty of Engineering, malikussaleh university, Bukit Indah, Lhokseumawe, 24353, Indonesia
  • Nura Usrina Department of Civil engineering, Faculty of Engineering, malikussaleh university, Bukit Indah, Lhokseumawe, 24353, Indonesia
  • T Mudi Hafli Department of Civil engineering, Faculty of Engineering, malikussaleh university, Bukit Indah, Lhokseumawe, 24353, Indonesia,
  • Syibral Malasyi Department of Civil engineering, Faculty of Engineering, malikussaleh university, Bukit Indah, Lhokseumawe, 24353, Indonesia
  • David Sarana Department of Civil engineering, Faculty of Engineering, malikussaleh university, Bukit Indah, Lhokseumawe, 24353, Indonesia,
  • Muhammad Muhammad Department of Civil engineering, Faculty of Engineering, malikussaleh university, Bukit Indah, Lhokseumawe, 24353, Indonesia

Keywords:

Earned Value Method, Cost Performance, schedule Performance, Project Monitoring, Construction Management

Abstract

This study applies EVM to the IAIN Lhokseumawe Laboratory Center Building Construction Project to evaluate its cost and schedule performance. The primary objective of the study is to assess how well the project adheres to its planned budget and timeline. Data was collected from project documents over the first 24 weeks, including progress reports and cost records. Key performance indicators (KPIs) such as Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV), and Cost Performance Index (CPI) were calculated. The results show that by the 24th week, the Schedule Variance (SV) is Rp 0 and the SPI is 1, indicating that the project is on schedule. Regarding cost, from Week 1 to Week 21, the project has incurred costs lower than planned, with a positive Cost Variance (CV) of Rp 12,927,390,000, and a Cost Performance Index (CPI) greater than 1 (1.11), indicating strong cost control and efficiency. Overall, the project is progressing as planned with excellent cost and time performance. The findings suggest that EVM is an effective tool for monitoring and controlling construction projects.

References

G. Prasetia, S. Sofyan, D. Sarana, N. Usrina, M. Maizuar, and F. Fadhliani, “Improving Improving Efficiency and Accuracy of Quantity Take-Off Through BIM Integration: A Case Study of the D Lecture Hall Building at Malikussaleh University,” Proc. Malikussaleh Int. Conf. Multidiscip. Stud. MICoMS, vol. 4, pp. 00013–00013, Dec. 2024, doi: 10.29103/micoms.v4i.893.

[2] M. I. Maromi and R. Indryani, “Metode Earned Value Untuk Analisa Kinerja Biaya Dan Waktu Pelaksanaan Pada Proyek Pembangunan Condotel De Vasa Surabaya,” J. Tek. ITS, vol. 4, no. 1, pp. D54–D59, Mar. 2015, doi: 10.12962/j23373539.v4i1.8970.

[3] Sunario Sunario, Syahrudin Syahrudin, and Riyanny Pratiwi, “Penerapan Model Pengendalian Waktu dan Biaya,” J. Mhs. Tek. Sipil Univ. Tanjungpura, vol. 3, no. 3, Dec. 2016.

[4] H. M. Sari, I. Hendriyani, and A. E. Widyaningrum, “Earned Value Analysis pada Proyek Pembangunan Gedung Arsip Kantor BPN: Earned Value Analysis of BPN Office Archives Building Projects,” J. Ilm. Tek. Sipil TRANSUKMA, vol. 3, no. 2, pp. 154–167, Jun. 2021, doi: 10.36277/transukma.v3i2.84.

[5] A. Husen, “Manajemen Proyek Perencanaan, Penjadwalan & Pengendalian Proyek,” Yogyak. Andi, 2009, Accessed: Jan. 07, 2025. [Online]. Available: https://scholar.google.com/scholar?cluster=1889284825863767537&hl=en&oi=scholarr

Downloads

Published

2024-01-31